Developments
The Pinnacle,
Southend

Contact us today

Conveniently located on the bustling Victoria Avenue, The Pinnacle will comprise 60 two bed apartments with parking.

A wide range of first-class amenities can be found within walking distance as well as excellent transport links making access to all parts of the town and neighbouring areas quick and easy.

Key points

  • Property type:
    Apartment complex
  • Location:
    Southend
  • Units available:
    60 in total, 1 & 2 bed apartments.
  • Guide price:
    £155,950 - £185,950
  • Predicted yield:
    7%

Development status: All apartments sold

Completion date: July 2017

Find out more info about the development

Download our brochure Contact us today

It's all about the location

The property & Investment

Payment plans

Find out more info about the development

Download our brochure Contact us today

The latest Development updates

Bathrooms and shower rooms being installed

Second fix electrics underway

Final floors under construction

The Pinnacle Site Update

Final floors are under construction

Kitchens being fitted

Carpentry is taking place

Bathrooms and shower rooms being installed

Painting is underway

Second fix electrics underway; heaters, sockets and switches being fitted.

The Pinnacle Update

Please see recent photos from The Pinnacle following a visit to Southend this week.

Progress is being made on all floors.

Level 1 & 2 – Stripped out, windows & partitioning in progress ready for first fix

Levels 4 & 5 – Windows fitted & first fix electrics and plumbing now complete, closing in and plastering to commence

Level 6 – Stripped out ready for first fix, all services and windows

Boarding out and mains water supply installation

Level 5 boarding out complete

Plumbing and electrics installed

'What's happening at Pinnacle'

 

  • Level 5 boarding out of all units is complete, 1st fix plumbing and electrics has commenced
  • Level 4 boarding out has started
  • Level 2/3 metal partitioning has begun to separate the individual apartments and communal areas
  • The plan for level 5 is to install the new UPVC windows, this will make the build water tight and kitchens can then be fitted 

Ready to install window frame

Preparing for window installation

Level 5 boarding out of individual apartments

Enjoying the views from Level 5!

Level 3 stripped out!

Pinnacle site visit - Latest News

We’re pleased to report some good progress from last week’s visit. Here’s an overview of what’s happening on-site now and over the next few weeks:

Level 5

Partitioning and boarding underway for each unit

Ceiling installation to commence week of 11th July

Interval wall division to commence week of 18th July

1st fix electrics, water and plumbing to be completed within next 4 weeks

Level 4

Following closely behind level 5 with the partitioning

Levels 3/2/1 stripped out, drainage in.

Window installation to commence end of July for approx. 3 weeks

 

 

Works to commence at Level 6 and move downwards through the development. New windows are being installed, followed by internal partitioning. First fix electrics and plumbing being done on this level

Level 6 strip out well underway