  • The development team submitted a planning application to discharge the Outline Planning Permission reserved matters planning conditions in February 2021.
  • Prosperity is currently working with the Norfolk Highways Department to design and procure the new site access roundabout situated on the A1122 main road.
  • The Prosperity Utilities consultant is with working with the gas, water, electricity and telecommunication service providers to design, cost and implement bringing the services to the site.
  • The Prosperity Homes site delivery team is being assembled to be in place by late October 2021.
  • Works targeted to commence on site Q1 2022.