February 19, 2021

JQ Rise Site Update Q1 2021

 

  • S.106 Agreement executed 23 October 2020.
  • The profession team to deliver the development has been appointed and are now working in conjunction with Interserve Construction Ltd to procure the Main Design and Build contract.
  • Demolition now complete
  • Further site investigation works and enabling works underway
  • To be followed by ground remediation, pile probing, piling obstruction removals and piling mat formation.
  • Design development & contract procurement to February 2021
  • Piling works to commence 1st week March 2021
  • Main Contractor targeted start on site March 2021.
  • Estimated Completions, Q3/Q4 2022

Related Updates

View all updates