The profession team to deliver the development has been appointed and are now working in conjunction with Interserve Construction Ltd to procure the Main Design and Build contract.
Demolition now complete
Further site investigation works and enabling works underway
To be followed by ground remediation, pile probing, piling obstruction removals and piling mat formation.
Design development & contract procurement to February 2021
Piling works to commence 1st week March 2021
Main Contractor targeted start on site March 2021.