The demolition works are complete and all the services to the site have been isolated.
Site Investigation works have been completed and report awaited that will influence the design of the foundations.
Section 106 Agreement has been complete and formal planning consent has been granted with the issuing of the Planning Decision Notice for the construction of 116 apartments.
Design delivery team is in the process of being appointed with the design development commencing February 2021.
Construction works targeted to commence on site September 2021.