May 21, 2021

Park View Site Update Q2 2021

 

  • The building has been demolished except for areas required for stability pending further site investigation works.
  • A schedule of works has now been prepared by the structural engineer that will allow for the safe completion of the demolition works.
  • All services to the site have been disconnected.
  • Ground investigation works have been completed and the final report has been issued.
  • Rights of Light survey is in the process of being prepared to assess any potential third party right of light injuries and to procure an insurance policy to cover off the risk.
  • The Architect, Structural & M&E Engineers have been appointed and are progressing the Stage 4/pre-construction design.
  • Information required to discharge the pre-commencement planning conditions is being assembled to submission to Birmingham City Council
  • Electrical supply / point of connection to the site has been secured and allocated to the development site.
  • Estimated Start on site: September/October 2021
  • Estimated Completion: Q3 2023