The Architect, Structural & M&E Engineers have been appointed and are progressing the Stage 4 / pre-construction design.
A Fire Consultant has been appointed to review the designs and specification for compliance with all current and emerging building fire legislation.
The piling and foundation designs are progressing in conjunction with the superstructure and initial discussions have taken place with potential contractors to carry out the works
The architect is developing the planning approved design to ensure compliance with the current Building Regulations and progressing the detailed construction drawings.
The design team are in discussions with the BCC planning department to change the external façade from metal cladding to brickwork.
An enabling works tender has been issued for pricing for the final demolitions and works along the boundaries to prepare the site for the commencement of the substructure works.
Temporary supplies for electricity and water to service the site during the construction phase have been organised.
Mobilisation has commenced for a start on site which is targeted for October 21.
The design team are progressing towards assembling fully detailed work packages to issue to the supply chain for pricing.
Electrical supply / point of connection to the site has been secured and allocated to the development site.