Fire protection to the ground floor steelwork complete.
Perimeter retaining walls and steel column concrete encasements complete
Steel frame preparation complete
HV sub-station installed, complete and secured
Main drainage connection works to the highway commenced.
Brick and blockwork progressing
Steel superstructure erection to completion W/c 18 January 2021.
External facade, upper concrete floors, internal partitioning & 1st fix electrical and plumbing works to closely following and co-ordinate with the steel frame erection programme.
The site will be open 7 days a week and operating extended working hours to meet the target completion date.