February 19, 2021

Moseley Gardens Site Update Q1 2021

 

  • All foundation substructures complete.
  • Under ground floor slab drainage complete
  • Ground floor slab has been cast.
  • Fire protection to the ground floor steelwork complete.
  • Perimeter retaining walls and steel column concrete encasements complete
  • Steel frame preparation complete
  • HV sub-station installed, complete and secured
  • Main drainage connection works to the highway commenced. 
  • Brick and blockwork progressing
  • Steel superstructure erection to completion W/c 18 January 2021.
  • External facade, upper concrete floors, internal partitioning & 1st fix electrical and plumbing works to closely following and co-ordinate with the steel frame erection programme.
  • The site will be open 7 days a week and operating extended working hours to meet the target completion date.
  • Estimated Completion: Q2 2021

Related Updates

View all updates

Moseley Gardens - November 19, 2021

Finished Bathroom

Moseley Gardens - November 19, 2021

Finished Kitchen

Moseley Gardens - November 19, 2021

Moseley Gardens Update Q4 2021

Read more

Moseley Gardens - August 27, 2021

1st fix Kitchen Installation

Moseley Gardens - August 27, 2021

1st fix Bathroom Installation