Severn House Site Update Q1 2021

 

  • Tower crane now dismantled.
  • Steel frame, precast concrete floor & staircases complete.
  • Roof covering complete
  • External facades progressing, brickwork, SFS to internal walls and partitioning.
  • Windows are being installed alongside the external facade.
  • 1st fix electrical and plumbing work progressing throughout the building.
  • Targeted to be “water-tight– by January 2021.
  • Estimated Completion: Q2 2021