About
About Prosperity Group
Our Rebrand
Contact Us
Why Invest with Prosperity Group
Why Invest in UK Property with Prosperity Group
Payment Plan
Meet Joe Billingham
Founder & CEO
Developments
All Developments
Current Developments
Under Construction
Completed Developments
Locations
UK
Birmingham
Nottingham
Investment Types
Investment Types
Buy-To-Let
Off-Plan
Student Accommodation
Traditional & Short Term Let
Smithfield House
Birmingham Property Investment
Insights
Property Investment
Is Buy-To-Let Worth It In 2026?
How To Find The Best UK Property Locations
Beginners Guide To UK Property Investment
Landlords
New Rules For Landlords 2026
How To Calculate What Rent To Charge
November Budget 2025: Impact On Landlords
Invest In UK Property From Overseas
United Arab Emirates
South Africa
Nigeria
Prosperity Racing
Find out more
Updates
Enquiries
T: +44 (0) 121 237 4610
February 19, 2021
Market Court Site Update Q1 2021
Soft strip out works complete
Minor demolition works progressing to form the apartment spaces to the 2
nd
floor apartments.
Internal courtyard decking progressing to completion prior to cutting out the existing roof to form the open space.
Internal drainage installed allowing raised communal corridors to be completed.
Sprinkler installation complete to 2
nd
& 3
rd
floors.
First fix electric and plumbing complete to the 3
rd
floor.
New external windows and doors fitted to the 3
rd
floor apartments
Dry lining complete to the 3
rd
floor prior to plastering commencing.
New windows to be fitted to the 2
nd
floor apartments
Drylining progressing to the 2
nd
floor alongside 1
st
fix electrical and plumbing
Estimated completion: Q3 2021
Related Updates
View all updates
Market Court
- November 26, 2021
Completed Bathrooom
Market Court
- November 26, 2021
Completed Bedroom With Skylight
Market Court
- November 26, 2021
Completed Kitchen
Market Court
- November 26, 2021
Market Court Q4 2021 – Completed
Read more
Market Court
- August 25, 2021
Kitchen/Diner
About
Payment Plan
Updates
News
T: +44 (0) 121 237 4610