February 19, 2021

Cathedral House Site Update Q1 2021

 

  • Works carried out within a Grade 11 listed building conditions.
  • Internal drainage completed
  • Acoustic matting laid to the upper floors
  • 2nd fix plumbing and electrics completed to Plots 1-6
  • Top floor stripped back to expose the roof timbers and to create the top floor apartments, Plots 7 & 8.
  • Majority of the plastering complete to the 1st and 2nd floor apartments and mist coat applied.
  • Joinery works progressing: – doors, frames architraves and restorations.
  • Restoration works progressing to the window linings, communal staircases, and wood panelling.
  • Replacement heritage sash windows have been manufactured and awaiting delivery and fitting on site.
  • Secondary glazing to be installed once the new sash windows have been fitted.
  • Kitchen and bathroom installation progressing
  • Woodwork preparation commenced prior to painting.
  • Estimated completion: Q2 2021

Related Updates

View all updates

Cathedral House - May 21, 2021

Windows & Secondary Glazing

Cathedral House - May 21, 2021

Apartment Entrance Lobby

Cathedral House - May 21, 2021

Living Room

Cathedral House - May 21, 2021

Bathrooms

Cathedral House - May 21, 2021

External Fa├žade / Scaffolding