May 21, 2021

Cathedral House Site Update Q2 2022

 

  • All windows are now refurbished and secondary glazing installed throughout
  • Bathrooms complete and hot water cylinders are now installed
  • Kitchens fitted, cooker extract fans and appliances to be installed
  • Kitchen tiling is progressing
  • First and second fix joinery work complete
  • Floor coverings progressing
  • Exterior painting finished
  • External scaffolding to be dismantled
  • Internal decorations progressing throughout the building
  • Estimated completion Q2 2021

Related Updates

View all updates

Cathedral House - August 27, 2021

Bathroom

Cathedral House - August 27, 2021

Staircase

Cathedral House - August 27, 2021

Living Room

Cathedral House - August 27, 2021

Kitchen

Cathedral House - August 25, 2021

Cathedral Site Update Q3 2021

Read more