  • Build completion is now concluded for all Chartwell apartments and with just the final finishes to conclude in the lower communal and lobby areas
  • Despite having been severely impacted by Covid-19 pandemic with a shortage of materials and labour– work has progressed massively in the communal areas
  • Building exterior clean up now concluded
  • Building control inspector has carried out pre-sign off visit– actual sign off due week commencing 24th August
  • All utilities connected to mains supply and commissioned
  • Final works for lower corridors and lobby– painting and flooring to be concluded
  • Lifts due to be commissioned 3rd week of August

Related Updates

View all updates

Chartwell Plaza - March 2, 2021

Finished bedroom

Chartwell Plaza - March 2, 2021

Finished duplex apartment

Chartwell Plaza - March 2, 2021

Finished apartment

Chartwell Plaza - March 2, 2021

Duplex Staircase

Chartwell Plaza - March 2, 2021

Duplex Staircase