October 2, 2020

H2 Site Update – Q4 2020

  • M&E 2nd fixed– floors Ground to 15
  • 2nd fixed Joinery– floors 1 to 15
  • All plastering and drylining complete
  • Decorated– floors 1 to 15
  • Carpets fitted floors 4 to 15
  • Ground and Lower Ground apartments to complete
  • External works to complete
  • Estimated Completion: Q4 2020