May 21, 2021

JQ Rise Site Update Q2 2021

 

  • The professional team to deliver the development has been appointed and are now working in conjunction with Tilbury Douglas to procure the main design and build contract.
  • June 2021 is the target date for procuring the main contractor
  • Further site investigation works and enabling works are progressing on site following the demolition
  • Ground remediation, trial pitting, pile probing, piling obstruction removals and piling mat formation are commencing
  • Piling works to commence July 2021
  • Main Contractor targeted start on site July 2021
  • Estimated Completion: 1st Phase, Q1 2023
  • Estimated Completion: 2nd Phase, Q2 2023

Related Updates

View all updates

JQ Rise - May 21, 2021

Excavators breaking up the existing floors slabs, crushing plant & piling mat stockpile

JQ Rise - May 21, 2021

Stockpile of crushed piling mat material

JQ Rise - February 19, 2021

Demolition and site clearance time lapse

Read more

JQ Rise - February 19, 2021

Site cleared

JQ Rise - February 19, 2021

Demolition and Site clearance