November 19, 2021

JQ Rise Update Q4 2021

 

• Ground remediation, pile probing, piling obstruction removals and the construction of the piling mat is complete.
• Sub-structures and ground floor slabs to commence on site in January 22.
• Concrete construction (off site) have commenced
• Major supply chain packages have been ordered and secured for delivery in line with construction; bricks, kitchens, bathrooms, flooring
• Temporary supplies for electricity and water to service the site during the construction phase have been organised.
• Mobilisation has commenced
• The design team continue to progress assembling fully detailed trade packages to issue to the supply chain for pricing.
• Electrical supply/point of connection to the site has been secured and allocated to the development site.