October 2, 2020
JQ Rise Update Q4 2020
Planning permission was granted on the 4 June for the 226 units
106 Agreement is progressing and will be executed September 2020
The profession team to deliver the development is being assembled along with discussions with a number of main contractors
Service disconnections to the existing are being procured prior to the October / November commencement of the demolition works
Design development continues
Targeted start on site January 2021
Related Updates
View all updates
JQ Rise
- March 11, 2024
JQ Rise Q1 2024
Read more
JQ Rise
- October 6, 2023
JQ Rise Q3 2023
Read more
JQ Rise
- May 31, 2023
JQ Rise Q2 Update 23
Read more
JQ Rise
- March 6, 2023
JQ Rise Q1 Update 23
Read more
JQ Rise
- December 6, 2022
JQ Rise Q4 Update 22
Read more
Home
Developments
Refer A Friend
News
Updates
About
Contact
T: +44 (0) 121 237 4610