August 25, 2021

Market Court Site Update Q3 2021

 

  • Communal carpets being laid
  • External decorations complete
  • Final remedial works being carried out to the apartments
  • Final Testing and Commissioning of the apartments and communal areas
  • Apartments being cleaned prior to handover.
  • Build complete w/c 6 September 21