Our Developments

We continue to strive to ensure that our clients receive the very best experience when investing in a Prosperity product. With over 56% of our clients going on to buy a second property after two years, that’s a great sign we’re getting it right.

The latest development updates

B1 Site Update

  • Glazing commenced in January 2018
  • First 15 kitchens now fully fitted
  • Tiling to all kitchens and bathrooms 90% complete
  • First fix electrics and plumbing complete
  • Second fix plumbing started
  • Plastering work 90% complete
  • Brickwork 80% complete
  • Estimated completion for development: Q2 2018

B1 Birmingham City Centre

Severn Street Site Update

  • Planning application was submitted in December 2017
  • Application decision due in March 2018
  • You can view details of the registered application by visiting Birmingham City Council’s planning portal and entering the reference number 2017/10465/PA
  • Visit Planning Portal

Severn House Birmingham City Centre

Moseley Gardens Site Update

  • Planning application was submitted in December 2017
  • Application decision due in March 2018
  • You can view details of the registered application by visiting Birmingham City Council’s planning portal and entering the reference number 2017/10701/PA
  • Visit Planning Portal

Moseley Gardens Birmingham City Centre

B5 Site Update

  • Following success of the pre-application process, we are currently finalising the full planning application which is to be submitted by the end of January. Response time from Birmingham City Council is currently 12 weeks.
  • Detailed design work is being conducted alongside the planning phase which, subject to planning approval, could result in construction commencing in June 2018.

B5 Kent Street Birmingham City Centre