October 2, 2020
Moseley Gardens Site Update Q4 2020
All groundwork foundation substructures complete
Under ground floor slab drainage complete
Ground floor slab has been cast
Steel frame transfer structure erected
Transfer concrete slab complete
Fusion site survey complete with erection of the superstructure due to commence late September 2020
Site accommodation relocated
Perimeter retaining walls and steel column concrete encasements progressing
High voltage electric cable ducting is being brought to the site
Related Updates
View all updates
Moseley Gardens
- November 19, 2021
Finished Bathroom
Moseley Gardens
- November 19, 2021
Finished Kitchen
Moseley Gardens
- November 19, 2021
Moseley Gardens Update Q4 2021
Read more
Moseley Gardens
- August 27, 2021
1st fix Kitchen Installation
Moseley Gardens
- August 27, 2021
1st fix Bathroom Installation