May 21, 2021
Moseley Gardens Site Update Q2 2021
Drainage connection to the main sewers is complete
Electrical sub-station installed and energised
Mains Water connected to the site
Brickwork, render preparation and window fixing progressing to the external facades
Concrete flooring is complete
Fire protection paintwork completed to the steel frame
Ground floor. Internal walls complete and M&E containment installed, riser cupboards and lift core formed
First floor apartments have been formed
First fix M&E & plumbing including sprinklers complete.
Fire stopping and pre plaster checks being progressed
Second floor apartments have been formed. Sprinklers and mains cold feed 1st fix M&E progressing to completion
Third floor internal partitioning and plaster boarding and cable containment is finished
Fourth floor internal metal stud partitioning to create the apartments and corridors is progressing
Fifth floor service holes are being cored through the concrete slabs intumescent painting is complete
All the works packages have been procured and programmed to start on site
The site will be operating a 7-day working week to maintain the construction programme to achieve the target completion date
Information being collated to discharge pre-occupation planning conditions prior to completion
Estimated Completion: Q3 2021
Related Updates
View all updates
Moseley Gardens
- November 19, 2021
Finished Bathroom
Moseley Gardens
- November 19, 2021
Finished Kitchen
Moseley Gardens
- November 19, 2021
Moseley Gardens Update Q4 2021
Read more
Moseley Gardens
- August 27, 2021
1st fix Kitchen Installation
Moseley Gardens
- August 27, 2021
1st fix Bathroom Installation