August 27, 2021

Moseley Gardens Update Q3 2021

 

  • Mains electric cabling being installed to all the apartments and IDNO fitted to all levels.
  • Internal substation complete and energised 
  • Roof waterproofed and brown roof being installed.
  • Water main connected and chlorinated. 
  • Main tank room complete and the plinth cast ready for water tank installation
  • Main sewer connection completed   
  • Mechanical and electrical distribution being progressed throughout the building.
  • M&E 1st fix installation completed to all level’s 
  • 2nd fix M&E progressing ground to second floor
  • Plastering complete to all apartments
  • Kitchen fitting completed to floors 1-4, Progressing on 5
  • Internal doors commenced to ground, 1, 2 & 3 floors
  • Final decoration commenced to level 1 & 2 
  • Bathroom sanitary ware being installed to all apartments up to level 3
  • Wall & floor tiling commenced up to level 3
  • All internal partitioning completed to all floors
  • MF ceilings to level 5 and communal areas  
  • Sprinkler installation to the 5th floor completed and pressure tested. 
  • Fire stopping completed to level 5 and commencing on communal areas
  • Brickwork, render preparation and window fixing progressing to the external facades.
  • All the works packages have been procured and programmed to start on site.
  • All the information has been submitted BCC to discharge the pre-occupation planning conditions prior to completion 
  • Due to the impact of the Covid pandemic and import issues relating to Brexit, the UK construction industry is currently experiencing severe material shortages and extended delivery timescales which is impacting on the delivery programme for Moseley Street. The Prosperity team are striving to mitigate these delay items by seeking alternative suppliers or amending the design to accommodate alternative materials. 
  • Estimated Completion: Q3 2021

Related Updates

View all updates

Moseley Gardens - November 19, 2021

Finished Bathroom

Moseley Gardens - November 19, 2021

Finished Kitchen

Moseley Gardens - November 19, 2021

Moseley Gardens Update Q4 2021

Read more

Moseley Gardens - August 27, 2021

1st fix Kitchen Installation

Moseley Gardens - August 27, 2021

1st fix Bathroom Installation